Construction Evolution
TRF IS OPEN AND ACCEPTING WASTE FOR DISPOSAL

Apr24: Partial earthworks filled with water

May24: Dewatering commences

Jun24: Bulk earthworks commence

Jul24: TRF office upgrade

July24: Bulk earthworks

Aug: Subsoil drainage

Sep24: Subsoil drainage

Oct24: Drainage sump

Oct24: Clay liner complete

Oct24: Liner install commences

Oct24: Weighbridge system installed

Nov24: Liner installation

Nov24: Monitoring boreholes

Nov24: Leachate Tank

Nov24: Lining Contaminated Water Dam

Nov24: Main Cell Lining

Dec24: Contaminated Water Dam Completed

Dec24: Landfill Cell Completed

Dec24: The construction Team

Jan25: Bidim layer installed for acceptance of waste.

Jan25: TRF IS OPEN - First waste arrives for completion of pioneering layer.